Compared with an owner-occupied house, rental work adds requirements at each step.
Surveys and reports
RCW 49.26.013 puts the duty to have a good-faith inspection performed on the owner or owner’s agent, and the written report goes to contractors before they bid.
Certified crews
State law requires removal by a certified asbestos worker under direct on-site supervision of a certified supervisor. L&I notice is required before projects over 48 square feet or 10 linear feet.
Records
Shipment records are the owner’s to keep. If the disposal site’s signed copy has not come back after 35 days, PSCAA expects follow-up, and a written report to the agency if 45 days pass; copies are retained for two years at least.