A survey written for the project answers the questions that decide cost and paperwork.
Quantities and notice
A positive result becomes a plan once it has measurements. Each structure gets a yearly allowance of 10 linear feet of friable pipe insulation or 48 square feet of other friable material before PSCAA wants notice, and L&I’s separate notice starts above 48 square feet or 10 linear feet.
Reports that no longer match the plan
A report speaks only for the materials and rooms it lists. An older one is useful where its samples match the current scope. Add a wall to a bathroom job or a second flooring layer, and those materials need their own samples.
What the City asks for
The City’s remodel brochure does not mention asbestos, and the residential matrix lists PSCAA notification under demolition only. A remodel survey is therefore a PSCAA and state obligation, not a Lakewood permit item.